Road resurfacing project begins Monday in Audubon County

News

April 11th, 2024 by Ric Hanson

(Audubon, Iowa) – The Audubon County Engineer & Secondary Roads Department, reports that on Monday, April 15th, a resurfacing project will begin on County Highway M66 (Bluebird Ave); 5 miles from Co. Hwy. F24 (150th St.) to the Audubon/Carroll County line (100th St.). M66 will be under construction. Construction is anticipated to be complete by the end of May, weather pending.
The project involves milling the existing road surface, widening and paving the four-foot shoulders, and resurfacing the 22-foot wide roadway, with asphalt. The roadway will be open to traffic during construction. Traffic Control consist of lane closures with flaggers and pilot cars. Audubon County ask travelers to plan accordingly and anticipate travel delays. Please abide the traffic control signage and reduce speed through the construction area.
Click on the link below for more info about this project.