Milling work to begin on Atlantic streets and alleys this week

News

October 25th, 2016 by Ric Hanson

Atlantic City Administrator John Lund reports Henningsen Construction plans to start milling streets tomorrow (Wednesday), as part of the City’s 2016 Street and Alley Improvement Project. Lund says the best case scenario would be to start paving 10th Street close to November 1st. Once crews get 10th done, Lund says they may leave for a few days to go do work in Anita job and let PCS (Precision Concrete Service, Inc., of Atlantic) stay ahead of them. After that they would come back and do the alleys/parking lots.

Earlier this year, the Atlantic City Council passed a Resolution “Authorizing bids for the 2016 Street and Alley Improvements.” The projects were finalized for the Fiscal Year 2016 Capital Improvement plan. Slightly more than 1.085-million dollars for the projects is being financed by the 2016 bond. $500,-thousand dollars is being used from the Local Option Sales Tax Capital Improvement Streets fund to pay for the remaining projects.

Those projects include:

  • 10th St. from Sunnyside Lane to the Hospital Drive (3″ Hot Melt Asphalt [HMA] Overlay).
  • Olive St. from 7th to 10th (3″ HMA)
  • Maple St. overlay from 9th to 10th
  • Birch St. overlay from 2nd to 3rd
  • Walnut/Elm alley from 4th to 5th
  • 3rd to 4th St. alley (Chestnut to Poplar)

The Alley’s include those from:

  • 4th to 5th Sts. (between Walnut & Elm)
  • 3rd to 4th Sts. (between Oak & Hazel)
  • 8th to 9th Sts. (between Chestnut & Walnut)
  • 2nd to 3rd Sts.(Between Maple & Linn)
  • 8th to 9th Sts. (Between Maple & Linn, and Poplar to Locust)
  • 7th and 8th Sts. (Between Poplar & Locust)
  • Alley by Gade Insurance
  • All alleys and downtown parking lots.